laying cable: A. put cable in the cable entrance hole well outside, use first installation has cable traction and coated with lubricating oil cable head of wire rope with the end of the cable connection, the other end of the rope through the cable pipe, dragging cable force uniform, check the cable drawing for jam phenomenon in the process, such as the tension is too large, should investigate the cause, problem solving, to continue pulling cable. B. power cable shall be separately through a tube hole. The same tube hole can wear into the three control cable. C. three-phase single-phase single