Practice Questions
INSTRUCTIONS: Note the most suitable answer for each multiple-choice question in the appropriate space on the answer sheet.
In which form of project organization would the project manager be likely to exercise the most control over project resources?
Strong matrix
Projectized
Project coordinator
Weak matrix
在哪一种项目机构里,项目经理对项目资源有最多的控制?
强矩阵
项目型
项目协调人
弱矩阵
Which of the following is a ground rule for project team building?
Do frequent performance appraisals.
Ensure that each team member reports to his or her functional manager in addition to the project manager.
Start early.
Try to solve team political problems.
下面哪一个是团队建设的基本原则?
频繁进行执行评价
保证每个队员除了向项目经理汇报,还向职能经理汇报
早点开始
试图解决团队政治问题
Project A is being administered using a matrix form of organization. The project manager reports to senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
The project manager will probably not be challenged by project stakeholders.
In this strong matrix, the balance of power is shifted to the functional line managers.
In this tight matrix, the balance power is shifted to the project manager.
In this strong matrix, the balance of power is shifted to the project manager.
项目A是实行矩阵结构管理。项目经理向为项目提供可以看见支持的高级副总裁汇报。这种情形下,哪个说法最好地描述了项目经理的相对权力?
项目经理可能不会被项目关系人挑战
在这个强矩阵里,平衡的权力移到了职能经理
在这个严密矩阵里,平衡的权力移到了项目经理
在这个强矩阵里,平衡的权力移到了项目经理
Adjusting the timing of tasks so that resources are not over committed is called—
Resource leveling
Pairwise trade-off
The Multiattribute Utility Theory
Resource infringement
调整任务的时间,以便资源投入不致过多叫做:
资源平衡
成对方式平衡
多功能应用原理
资源破坏
Which of the following factors contributes the most to team communication?
External feedback
Performance appraisals
Smoothing over of team conflicts by the project manager
Collocation
下面哪一个因素对团队沟通贡献最大?
外部反馈
执行评价
项目经理消除团队冲突
排列
Project team members who work in different locations tend not to see themselves as a team or unified grou
您可能关注的文档
- php通用检测函数集【DOC精选】.doc
- Phrase translation【DOC精选】.doc
- Physical Layer for WN【DOC精选】.doc
- Phylip中文使用说明【DOC精选】.doc
- physio_paper【DOC精选】.doc
- piccx单片机原理及应用【DOC精选】.doc
- Pick公式【DOC精选】.doc
- PIC单片机C语言编程实例一【DOC精选】.doc
- PIC单片机的C语言应用下的函数库【DOC精选】.doc
- PIC单片机资源【DOC精选】.doc
- 第1章因式分解 自主学习同步练习题 2023—2024学年鲁教版(五四制)八年级数学上册.docx
- 2023-2024学年河南省焦作市八年级(上)期末数学试卷.doc
- 2023-2024学年黑龙江省哈尔滨市呼兰区顺迈学校九年级(上)月考数学试卷(9月份)(五四学制).docx
- 2023-2024学年浙江省湖州市长兴县等2地七年级(上)期末数学试卷.pdf
- 2023-2024学年江苏省无锡市梁溪区七年级(上)期末数学试卷.pdf
- _吉林省白城市大安市2023-2024学年下学期期末统考 七年级数学 试题.docx
- 山西省晋中市2023—2024学年上学期七年级数学期末考试卷.pdf
- 6.3正方形的性质与判定 同步测试题 鲁教版(五四制)八年级数学下册.docx
- 2022-2023学年四川省眉山市洪雅实验中学八年级(上)期末数学试卷.pdf
- 2023-2024学年安徽省合肥市瑶海区七年级(上)期末数学试卷.docx
文档评论(0)