1.You have been assigned as project manager on what could be a bet the company project. If the project is successful, management will be carrying you around on a sedan chair, if it fails, you will be in the unemployment line. You realize that to be successful you need to exercise maximum control over project resources. Which form of project organization should you establish for this project? A. Strong matrix B. Projectized C. Project coordinator D. Weak matrix 1. 你负责管理的一个项目, 这个项目对你来说是成败在此一举。 如果项目成功, 那么你的前途无量;如果项目失败, 那么你就要被炒鱿鱼。 你意识到:??为了使项目成功,你必须对项目资源具有最大程度的控制。 那么你预备建立哪一种项目组织形式来达到你的目的 A. 强矩阵 B.