施工日志(国外英语资料)
施工日志
2011/7/13
(1) masonry retaining wall and ground concrete in No. 5 workshop.
(2) for 9 hours and 30 minutes of leveling, send 70 yuan freight equipment.
(3) villa foundation attached to the cultural stone, stone powder 1 vehicles, 200 yuan
2011/7/14
(1) masonry retaining walls and plastering.
(2) the villa foundation is attached to the cultural stone.
(3) the excavator works 5 hours, and the highway carries 26 pieces of stones.
(4) buy Bedding and so on, spend 500 yuan, Lian Pengyu borrow 500 yuan.
?
2011/, 7/? 15?
(1) garage facade plastering.
(2) excavator leveling two workshop, road 2 hours, 0 minutes.
(3) south all the way slotting, four storehouse ground hits the concrete.
(4) 1.5 hours of stone bags on the south side of the 6 hook workshop of road excavator.
(5) the Sun Baoyu engineer team straightens up the reinforcement.
12:27, 2011/7/16
(1) South Road slotted, 4 workshop masonry foundation brick mold.
(2) external installation borrow Sun Baoyu two people, two days.
21:52, 2011/7/17
(1) hit the ground brick mold.
(2) borrow 2 people to install.
(3) rain, buy plastic cloth 20 meters, spend 120 yuan.
(4) digging well by excavator.
21:39, 2011/7/18
(1) column foundation concrete, under the embedded 4# warehouse to hit the ground.
(2) to the District rent the steel pipe failed. Buy cauliflower 158 yuan, drive shaft 100 yuan
(3) steel structure upper wall panel.
21:31, 2011/7/19
(1) column foundation concrete, under the embedded 4# warehouse to hit the ground.
(2) steel structure comes 8 people.
(3) fixed steel pipe, deposit 1000 yuan.
12:12, 2011/7/20
(1) the column foundation is made of concrete, and the steel pipe is rented and the steel pipe is drawn. Freight 250 yuan, deposit 22000 yuan
(2) 5# workshop ceiling, 6# plant surrounding the ground to play concrete.
(3) leveling South Road backfill stonework and 4# foundation.
(4) the excavation time of the 5#6# workshop is 4 hours.
(5) highway excavator, hammer, 6# workshop, north side, front stone
11:59, 201