- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
房建施工技术(国外英文资料)
房建施工技术
1. how to control the axis, elevation and verticality of high-rise buildings?
A. in the underlying set of control lines, at the same time on each floor to set the 200*200 mm wire hole number (control line at the bottom of the hole position alignment), management line in the discharge line hole side mounted vertical vertical laser instrument, control line to control the axis of each layer, vertical elevation, and more to review the control, the difference is very small
Two. How long will it take for the concrete to be removed?
The concrete structure, reached a certain intensity, can tear open mode. Mainly through the strength of the concrete block under the condition of the maintenance to determine when can be removed, the template removal date should be determined by the structural characteristics and strength of concrete to achieve.
The removal period of the cast-in-place concrete structure:
1. non load side formwork should be in the concrete strength to ensure that its surface and edges and corners are not damaged by dismantling the template, it can be removed, generally twelve hours later;
2. the load-bearing formwork shall be removed only after the concrete reaches the following strength (as per the percentage of the design strength grade):
Plate and arch:
Span is 2M and less than 2m 50%
The span is greater than 2m to 8m 75%
Beam (span 8m and less than 8m) 75%
Load-bearing structure (span greater than 8m) 100%
Cantilever and cantilever plate 100%
3. reinforced concrete structures such as formwork and bears a part of the load in the concrete does not meet the required strength, through calculation, strength check of structure in the actual load.
4. the structure of the dismantled formwork and its support shall be allowed to bear all the calculated load after the concrete has reached the design strength. No overloading shall be allowed during construction, and excessive building materials shall not be piled up. When the construction load is greater than th