Residential Development - Cash Flow Forecasting Estimated project revenues, costs and timing Current price for townhouses $270,000 Price escalation per month 0.50% Selling programme: 1 sold on building completion and then 1 per month. Marketing costs $15,000 plus $10,000 per townhouse Design and planning fees $60,000 in month 2 Construction costs Site works $45,000 in month 3 Building $625,000 paid in 4 stages, 2 monthly from month 4. Building contract permits contractor to recover increases in material prices and wages during construction. Esti