余热锅炉事故处理规则(Waste heat boiler accident handling rules)
余热锅炉事故处理规则(Waste heat boiler accident handling rules)
3.1
Water shortage phenomenon
3.1.1
The water level is below normal.
3.1.2
The alarm has a low water level signal.
3.1.3
The temperature of superheated steam rises or decreases when water shortage is serious.
3.1.4
The water supply flow is not normal less than the evaporation (the water cooling wall pipe or the coal tube rupture is more than the amount of evaporation).
3.2
Water shortage
3.2.1
The operator was negligent in monitoring inadequate or incorrect water levels.
3.2.2
The automatic water supply regulator failed to detect in time.
3.2.3
The water gauge indicates incorrect operation of the operator.
3.2.4
Drop the water supply pressure due to a failure of the pipe or water pump
3.2.5
Boiler discharge valve leakage or discharge without contact with the furnace.
3.2.6
The wall of water cooling wall tube or the wall of the economizer is broken.
3.2.7
Isolate the valve core from the water pipe.
3.3
Water shortage treatment
3.3.1
When the pressure of the boiler and water supply is normal, and the water level in the drum is lowered to normal water level (i.e., slight water shortage), the following measures should be adopted:
A. conduct the control of the water level and the cleaning of the bubble water gauge to check if the instructions are correct.
B. The water supply will be automatically changed to the on-site bypass to increase the water supply.
3.3.2 rainfall distribution on 10-12
If the water level in the drum is still low after the treatment, all water valves should be closed and the discharging valve and the discharge valve should be closed, such as the total valve of the discharging valve.
3.3.3
If the above measures are taken, the water level will continue to decline, and the minimum water level shall be allowed to report to the workshop or factory to reduce the boiler load gradually.
We do
If the water level of the drum is not visible due to the negligence of the operator, the water level cannot be de
您可能关注的文档
- 东风4检查(Dongfeng 4 inspection).doc
- 丝杠机械加工工艺设计说明书(Design instruction manual of screw machining process).doc
- 丝瓜络《中国药典》(Silk gourd Chinese pharmacopoeia).doc
- 丝网印刷中常见问题解答(A common problem solution in silkscreen printing).doc
- 两次调气门方法(Two valve control methods).doc
- 两阶段算法求解线性规划问题(运筹学实验)(Two-stage algorithm for solving linear programming problems (operational research experiment)).doc
- 严密性试验方法及标准(Strict test methods and standards).doc
- 个人2003年个人工作总结(Personal 2003 personal work summary).doc
- 个人的发展与公司的关系(Personal development is related to the company).doc
- 个板块龙头股(A plate leading stock).doc
- Darzalex Intravenous Infusion 100 mg, Darzalex Intravenous Infusion 400 mg(Daratumumab,达雷木单抗重组点滴静注)的NDA审评信息(PMDA).pdf
- Dysval Capsules 100×40mg(Valbenazine Tosilate 缬苯那嗪胶囊)的NDA审评信息(PMDA).pdf
- 盐酸克林霉素磷_过氧化苯甲酰复合凝胶(Duac Combination Gel)的NDA审评信息(PMDA).pdf
- DB13_2322-2016_工业企业挥发性有机物排放控制标准_河北省.docx
- DB13_T1266-2010_河北省商品林经营技术规程_河北省.docx
- DB12_T3007-2017_混合气体气瓶充装规定_天津市.docx
- DB12_T1301-2023_中小流域面雨量等级_天津市.docx
- DB13_T1246-2010_主要矿山废弃地植被恢复技术规范_河北省.docx
- DB13_T1251-2010_牛出血性白血病防治技术规程_河北省.docx
- DB12_T1300-2023_旅游气象适宜度评价规范_天津市.docx
文档评论(0)