变压器的大修项目及要求(Transformer overhaul projects and requirements)
Transformer overhaul projects and requirements
1. hanging bell bell or hanging body overhaul:
2. coil, lead and magnetic (Electrical) rating device overhaul
3. iron core, iron core fastener (through screw clamps, strap, strap, etc.) the pressure screw connecting pieces and even repair tablets
4. tank and accessories overhaul, including casing, moisture absorber and so on
5. maintenance of auxiliary equipment such as cooler, oil pump, fan, valve, pipe and so on
6. maintenance of safety equipment
Maintenance of 7. oil protection device
The effect of temperature measuring device 8., gas relay (pressure protector) effect
9. maintenance and test of operation control box
10. overhaul of no excitation tap changer
11. replacement of all sealant gaskets and component leakage test
12. drying the insulation of the machine when necessary
13. transformer oil treatment (vacuum filter oil) or oil change
14. clean the tank and do fuel injection paint and anti-corrosion treatment
15. after the overhaul test and trial operation
What are the items of power transformer inspection and maintenance?
I. overhaul
Overhaul cycle is generally 5 years. Its overhaul items are:
(1) maintenance of shell and oil.
Check and clean the shell, including the top cover, oil conservator, high and low voltage insulating sleeve, safety air passage, radiator and so on, and eliminate the leakage.
Filter oil or oil change according to transformer oil condition.
Inspect and repair earthing device.
Re coat the case when necessary.
(2) overhaul of core and winding.
Check core grounding and insulation piercing screw; inspection and cleaning winding and winding wire clamping device, etc..
Check whether the winding insulation is good and whether the gasket is firm, there should be no coil looseness, deformation and displacement, as well as the primary and secondary side winding asymmetric phenomenon of two.
(3) overhaul of tap changer.
Check and repair tap
您可能关注的文档
- 桂林中医院(Guilin Hospital of traditional Chinese Medicine).doc
- 广工金材专英翻译(Guang Gong Jin Ying Ying Ying Ying).doc
- 海上遇难的种种自救(Self help at sea).doc
- 海虾淡水养殖技术要点(Shrimp aquaculture techniques).doc
- 海虾淡养技术(Shrimp light curing technology).doc
- 广河中学简介(Guanghe middle school.).doc
- 广告摄影技巧(Advertising photography skills).doc
- 广联达安装算量gqi2011新增功能(A new gqi2011 glodon installation).doc
- 广联达安装算量识别顺序(Glodon count the amount of installed recognition sequence).doc
- 海贼王悬赏(One Piece offers a reward).doc
- 2024新疆科技职业技术学院招聘笔试真题及答案详解一套.docx
- 2024年黑龙江商业职业学院招聘笔试真题及参考答案详解1套.docx
- 2024广西工程职业学院招聘笔试真题参考答案详解.docx
- 2024淮北职业技术学院招聘笔试真题附答案详解.docx
- 2024江阳城建职业学院招聘笔试真题及答案详解一套.docx
- 2024浙江农林大学招聘笔试真题含答案详解.docx
- 2024江苏农牧科技职业学院招聘笔试真题及答案详解一套.docx
- 2024新疆工业职业技术学院招聘笔试真题及参考答案详解.docx
- 2024年黑龙江交通职业技术学院招聘笔试真题及参考答案详解一套.docx
- 2024新疆能源职业技术学院招聘笔试真题及参考答案详解1套.docx
文档评论(0)