索网幕墙过室内外脚手架配合进行安装
索网幕墙通过室内外脚手架配合进行安装。
Cable-net curtain wall will be erected under the cooperation of indoor and outdoor scaffoldings.
2.1安装流程测量放样→安装→索网安装→调整→玻璃安装→调整→清洁打胶。→ Steel column installation→ Cable net installation→ Adjustment→ Glass installation→ Cleaning and sealant installation
2.2测量放样首先依据总包单位的±0.000以及轴线进行复核。复核完毕,符合要求后,依据轴线与垂直索相对位置,进行拉索平面校准,将垂直索线弹在地面上,如图示。±0.000 of the general contracting work unit and axial line. If it meets the requirements after double check, conduct cable plane calibration as per axial line’s relative position with the vertical cable and snap the vertical cable line onto the ground just as the following picture shows.
将水平索拉点用墨线弹在结构立面上,如图示。
Snap the horizontal cable’s tension point with ink line onto the structure fa?ade as the picture shows.
2.3钢柱安装
(1)钢索的预拉
(1)Pre-stretching of the steel cable
索网在建设时必须施加预应力。具体的做法是,按设计所需预应力的 60%~80%张拉索网的钢索,然后自然放松钢索一段时间。如是重复几次,即可完成索网的预拉工作。
Pre-stress must be inflicted during the cable net construction. The concrete practice is: stretch the cable net’s steel cables as per 60%~80% of the pre-stress required by the design and loosen the steel cable for a period of time naturally. Repeat this several times and the pre-stretching of the cable net is completed.
(2)索网就位
(2) Cable net setting
1)借助于临时支承,将已经预拉并按准确长度准备好的垂直索就位。
1) Set the vertical cables that has been pre-stretched and prepared as per accurate length with the aid of temporary supporting.
2)将水平钢索与已安装在垂直钢索上的扣件连接,并在锚固端张拉。
2) Connect the horizontal steel cables to the fasteners already installed on the vertical steel cables and stretch it at the anchor end.
索网校正并经监理验收合格后进行玻璃夹安装。安装时,根据玻璃夹位置图安装,定位玻璃夹。
The glass will be installed after the cable net has been corrected and accepted by the supervision. Install and locate the glass clip as per the glass clip location map during installation.
2.6玻璃面板安装
2.6 Glass panel installation
(1)玻璃安装之前应再次调整钢拉索,达到设计要求的分格尺寸。
(1) Steel cables shall be adjusted once again before the glass installation to meet the module dimension required