The Performance Prediction of A TBM in Difficult (性能预测TBM的困难)
The Performance Prediction of A TBM in Difficult
Ground Condition
Nuh BİLGİN, Cemal BALCI, Hakan TUNÇDEMİR, Şinasi ESKİKAYA
Department of Mining Engineering, Technical University of İstanbul, Turkey.
Mustafa AKGÜL, Melih ALGAN
STFA Construction Company, Turkey.
ABSTRACT: Tuzla-Dragos Sewerage Tunnel is situated in the Asian Side of Istanbul. A
detailed laboratory full-scale cutting tests were used on rock samples collected from tunnel
side. The equipment used for the tests is developed under NATO TU-Excavation Project in
Istanbul Technical University, Mining Engineering Department. Test results were used to
predict the cutting performance of a TBM. Actual and predicted values are later compared
using a rating system for machine utilization.
RÉSUMÉ :Le tunnel Tuzla-Dragos construit pour le reject d’eau pollué est situé au coté
l’Anatolie de la Turquie. Pour réaliser les essais on a développé un équipements dans
l’Université Technique d’Istanbul à la Faculté des Mines à l’aide du financement obtenu par
le project d’excavation NATO-TU. On a profité des résultats des essais pour la suggestion de
la performance d’excavation TBM. En comparant les mesures en place avec certaines
suppositions, on a fait des critiques sur la validité du module
1 INTRODUCTION
Prediction of a TBM (Full Face Tunnel Boring Machine) performance plays an important
factor in decision making for a tunnel contractor. There are several factors which govern the
performance of a TBM. These are mainly rock mass properties, geological conditions,
machine parameters, machine maintenance facilities, experience of contractors and TBM
operator. Several prediction models were used in the past to
您可能关注的文档
- THE MECHATRONICS HANDBOOK(机电一体化手册).pdf
- The Mechanism of Stress Corrosion Cracking in (应力腐蚀开裂的机理).pdf
- The Medical Transcription Workbook HPI(现病史医学转录工作簿).pdf
- THE MELIN ADVANTAGE Melin Tool(梅林优势梅林工具).pdf
- THE MENTAL STATUS EXAMINATION Brown (布朗的精神状态检查).pdf
- The Mercedes-Benz OM 651 Four-Cylinder …(651梅赛德斯-奔驰OM四缸u2026).pdf
- The Method Chapter uk.sagepub(该方法uk.sagepub章).pdf
- The MERCK Manual merckbooks(默克手册merckbooks).pdf
- THE METHOD FOR DETERMINATION OF THE (的测定方法).pdf
- The Method of Calculations of the (的方法计算的).pdf
文档评论(0)