活动脚手架搭设方案
活动脚手架搭设方案
Plan of Erection Procedures for Movable Scaffold
目录TABLE OF CONTENTS
1. Prepare explanation编制说明 3
2.Reference编制依据 3
3.Descprition of gantry搭设方案 3
1. Prepare explanation编制说明
2.Reference编制依据
现行国家施工规范、标准及规程(但不限于National construction criterion, standard and regulations(not limited)
《建筑施工高处作业安全技术规范》(JGJ80-91)Safety Technical Specification on Working in High Place of Building Construction JGJ80-91
《建筑施工扣件式钢管脚手架安全技术规范JGJ130-2001
《Technical Code on the Safety of Scaffold of Steel Pipes in Fastener Connection for Building Construction》 JGJ130-2001
3、搭设方案 Plan of erection
3.1 前提条件 Prerequisites
移动式脚手架由扣件式脚手架搭设。
The movable scaffold must be built in fastener connection.
移动式脚手架的各部件在使用前须经过项目部和**的***人员检查合格。
All parts must be checked by **** and the safety supervisors of***** as ok before being put to use.
移动式脚手架不得人力搬运,必须配有脚轮;所有脚轮都须配有自锁装置,使移动脚手架在使用时保持不动。
The movable scaffold must be handled with castors. No manual efforts are allowed in this regard; all castors are equipped with self-locking device, which serves to hold the movable scaffold still when it is use.
移动式脚手架的作业平台必须满铺脚手板,临边必须搭设踢脚板.
Boards must be completed paved tharough the movable scaffold’s operation platform, and toe-board must be provided on platform’s edges
移动式脚手架必须设置梯子,供上下进出;梯子与脚手架必须固定好或整体制作,确保使用时梯子与脚手架不会分开。
Ladder must be provided for the movable scaffold to allow climbing; sufficient fixation of the ladder and scaffold must be provided or they should be provided as a package whole, hence sparing any hazard of disengagement in future use.
3.2移动式脚手架、梯子的搭设 Erection of movable scaffold and ladder
移动式脚手架跟其它脚手架一样必须由架子工搭设。操作平台不大于2m×2m
Only scaffold setters are allowed to set up movable scaffold, as is must with other scaffold types. The platform area should not be bigger than 2m×2m.
移动式脚手架搭设过程中或整改时,禁止架子工以外的职工使用;搭设完毕由HSE部门组织检查,检查合格并挂牌后方可使用。
During the erection or modification, no workers are allowed to use this scaffold short of scaffold setters; the scaffold should not be put to use until it has be
文档评论(0)