南水北调中线工程大型渡槽槽身支撑架方案设计和安全分析

南水北调中线工程大型渡槽槽身支撑架方案设计和安全分析   摘要:南水北调中线干线工程在石家庄以南分布有20多座渡槽,槽身支承结构施工方案的制定和实施,是整个渡槽工程施工的核心技术,渡槽上部结构施工过程的稳定问题对工程质量和安全产生巨大的影响。也是槽身施工的重点和工作量最大的工作。其方案必须安全可靠、经济实用,需要根据实际地质情况和上部结构详细进行分析研究确定。本文以??河渡槽为例进行了叙述。   关键词:中图分类号:TU74文献标志码:A文章编号:   1672-1683(2015)001-0176-04   The Middle Route of South-to-Nouth Water Transfer Project with supporting frame design and safety analysis for large aqueduct   ZHANG Wen-hu1,WANG Shu-xin2,LIU Jian-feng3   ((1.Hebei Prov incial Bureau of Constructi on Administration for the South-to-North Water Diversion Project,Shijiazhuang 050035,China;2.Hebei Water Conservancy Engineering Bureau,Shijiazhuang 050021,China;3 Construction Administration Bureau of Middle Route Project in South-to-North Water Division,Shijiazhuang 050053,China)   )   Abstract:There are more than 20 aqueducts of the Central Line Project of South-to-North Water Diversion distributed in the south of Shijiazhuang.How to formulate and implement the construction scheme of the aqueduct body supporting structure is the core technology of the whole aqueduct project construction.The stability of the upper structure construction process of the aqueduct has a great impact on the quality of the project and the safety.And it is also the key point of construction of the aqueduct body,which needs a lot of work.The scheme of the aqueduct body supporting structure must be safe and reliable,economical and practical and determined according to the practical geological conditions and the upper structure.This thesis gives a full account of the Zhi River aqueduct.   Key words:   1槽身结构与工程量   ??河渡槽由进出口渐变段、进出口检修闸段、进出口连接段和槽身段组成,起点桩号150+541,终点桩号150+999。其中:槽身段起点桩号150+621 m,终点桩号150+891 m,共分9跨,单跨长30 m,全长270 m。   渡槽上部槽身为三槽一联带拉杆预力钢筋混凝土梁式矩形槽,槽身宽度243 m,上部翼缘外侧宽度255 m。   槽身过水断面尺寸70 m(宽)×67 m(高)×3槽,槽内设计水深558 m,加大水深598m,渡槽纵坡i=1/4100。30 m跨单槽断面尺寸为70×67 m,边墙厚06 m,顶部设27 m宽人行道板;中墙厚07 m,顶部设30 m宽的人行道板。   经计算,槽身现浇混凝土10 6645 m3,钢筋制安1 0688 t,预力钢筋制安3802 t,预力钢绞线制安2187 t。单跨槽身混凝土1 1575 m3,各类钢筋钢绞线178 t。   2槽身施工支撑系统方案

您可能关注的文档

文档评论(0)

1亿VIP精品文档

相关文档