SampleOperations And Supply Chain Management样品的运营和供应链管理
Chapter 05
Projects
?
True / False Questions?
1.
Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project.??True????False
?
2.
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.??True????False
?
3.
The second step in managing a project is writing the Statement of Work.??True????False
?
4.
An event unit package is a subdivision of a project.??True????False
?
5.
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.??True????False
?
6.
A work breakdown structure is used in project management but it is not used when the critical path method is involved.??True????False
?
7.
The fact that organizations are flattening is one of the reasons that project management is important.??True????False
?
8.
The Gantt chart is an example of a project control chart.??True????False
?
9.
Upper level management must decide between pure, functional, and matrix structures as ways to organize projects.??True????False
?
10.
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.??True????False
?
11.
One of the advantages of a functional project organizational structure is that a team member can work on several projects.??True????False
?
12.
A matrix project attempts to blend properties of functional and pure project structures.??True????False
?
13.
A matrix project structure is often referred to as a skunkworks.??True????False
?
14.
A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.??True????False
?
15.
The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network o
您可能关注的文档
最近下载
- 专业月嫂服务合同范本及注意细节.docx VIP
- 《煤化学》全套教学课件.pdf
- 铁路工程沉降变形观测作业指导书.docx VIP
- tsg zf001-2006 《安全阀安全技术监察规程》新.pdf VIP
- 2024年山东省淄博市高青县中考一模英语试题.docx VIP
- 2015款一汽大众高尔夫_汽车使用手册用户操作图示图解详解驾驶指南车主车辆说明书电子版.pdf
- 铁路工程沉降变形观测与评估技术2015年稿.pdf VIP
- JBL JBL专业 无线麦克风系统 VM200 用户手册.pdf
- 相贯体的投影与相贯线一相贯体及相贯线的概念相贯体两相交的立体相贯线相交立体表面的交线立体相贯三种情.ppt VIP
- 妊娠期心肺复苏中国急诊专家共识测试卷及答案.docx
原创力文档

文档评论(0)