桥梁限高架施工组织设计
永煤公司铁路运输处
目 录
1 工程施工模式···············································································2
2 工程施工方案···············································································2
2.1 开工前交底及开工准备会························································2
2.2 钢结构制作················································································2
2.3 现场施工····················································································3
2.4 竣工验收····················································································3
3 限高架施工图纸···········································································4
4 施工安全措施···············································································7
4.1 一般要求····················································································8
4.2 钢轨搬动及运输安全································································8
4.3 钢架加工安全措施····································································8
4.4 用电安全····················································································8
4.5 基坑施工····················································································9
4.6 钢结构(钢轨)吊装安全························································9
5 施工所需机具、材料···································································9
4.1 施工所需机械、工器具····························································9
4.2 施工所需材料············································································9
6 工程概算·······················································································9
桥梁限高架施工组织设计
1 工程施工模式
该工程为车集线地销路立交桥、雪枫路立交桥的限高防护架施工,防护架使用43kg/m钢轨制作,由铁运处组织施工,具体分工为检修段负责按照图纸加工限高架,工务段负责限高架加工的监督和现场安装,供应科负责相关机具、材料的租用和购买。
施工负责人分别为:
检修段限高架制作负责人×××,分管领导×××。
工务段施工负责人:×××;分管领导×××。
主管科室管理人员:×××;负责领导×××。
2 工程施工方案
2.1 开工前交底及开工准备会:
运输科组织工程相关单位现场交底,确定限高架设置的详细位置(明确到具体尺寸)、高度。同时举行开工准备会,统一协调限高架制作与施工过程中的责任分工及注意事项,明确施工各工序检查和验收的步骤,确定开工时间。
2.2 钢结构制作:
钢结构制作前,工务段试验5根钢轨按图纸的布置方法和跨度安装后,其下垂量达到多少,以根据桥梁高度
文档评论(0)