古城墙修缮工程施工组织-2013.9.3新
历史文化名镇崖州古城城墙修缮
工程
施
工
组
织
设
计
编制人:
审核人:
审批人:
编制单 :
1 35
第 页 共 页
目 录
一、编制说明············································································3
二、工程概况············································································3
三、主要工程指标······································································4
四、施工前的准备······································································4
五、古城墙修缮施工方案 (待定)···············································11
六、拟投入的主要施工机械计划表···············································22
七、劳动力安排计划·································································23
八、确保安全生产的技术组织措施···············································25
九、确保工期的技术组织措施·····················································31
十、确保文明施工的技术组织措施···············································33
十一、施工环境保护、水土保持和文物保护等措施和方案·················35
十二、合理化建议及降低工程成本措施·········································36
十三、确保工程技术的组织措施··················································37
十四、季节性施工措施······························································37
十五、保修回访措施·································································38
十六、施工进度计划表······························································38
2 35
第 页 共 页
一、编制说明
(一)、 编制目的
编制本施工组织设计为该工程施工组织提供科学、严密完整的纲领性文件,
为工程提供科学、严密的施工方案,以确保优质、高效、低耗、安全、文明地
完成工程的建设任务。
(二)、 编制依据
1、建设单位提供的历史文化名镇崖州古城城墙修缮 (一期)工程项目建设
工程施工图纸及招标文件及招标答疑。
2、《中华人民共和国文物保护法》。
3、《中华人民共和国文物保护法实施条例》。
4、《革命建筑、古建筑和石窟寺维修保护工程管理条例》。