山东科技大学学士学位论文 矿区概述
PAGE
PAGE 104
梁宝寺二号井毕业设计学士学位论文
摘 要
本文根据对梁宝寺二号井资料的学习和研究,遵照《煤矿安全规程》和《煤炭工业设计规范》的要求,充分运用所学的知识,根据3煤的开采范围,计算出3煤的储量、生产能力和服务年限,对梁宝寺二号井行设计。在设计中尽量做到安全、高效、绿色,把梁宝寺煤矿二号井建成高产高效的矿井,为我国的煤炭生产作出贡献。
本设计是梁宝寺煤矿二号井新井设计。本井田面积约31.4km2,可采储量90.9Mt。生产能力1.2Mt/a,服务年限54.1年。
矿井采用立井单水平开拓,水平标高-1020m,采用上下山开采,采区划分尽量以自然断层为界,以改善大巷及上下山压力状况,将井田划分为六个采区。
采区采用单一走向长壁、后退式全部跨落法采煤、采煤工艺为综采放顶煤采煤,每一采区设3条上山即运煤、轨道和回风上下山,中部车场联系顺槽和上下山。
矿井初期采用中央边界通风,风井口安装轴流式风机进行抽出式通风,并制定了安全技术措施。
关键词:储量计算;矿井开拓;井田划分;巷道布置
ABSTRACT
Based on the information of the new Station coal study and research, in accordance with the requirements of the Coal Mine Safety Regulations and the coal industry design specifications, and fully use the knowledge learned, according to the coal mining area, the calculated coal reserves regional design, production capacity and length of service.. As far as possible in the design of safe, efficient, green, Liangbaosi coal mine built a high yield and efficiency of mine, to contribute to Chinas coal production.
The design is LIANGBAOSI 2nd Mine well design. The minefield area of about 31.4km2 recoverable reserves of 90.9Mt. Production capacity of 1.2Mt / a, the service life of 54.1 years.
Mine using the vertical shaft single-level open up the level of elevation-1020m, using the park mining division of mining area is bounded by natural faults as far as possible, to improve the roadway and the pressure on the downhill situation, Ida is divided into six mining area.
Using a single long wall mining area, retreat all across the drop-mining method, mining process is fully mechanized top coal mining to each mining area is located three mountains namely coal, rail and air return down the mountain, the central depot the contact crossheading and the park.
Mine early use of the central boundary ventilation, wind wellhead installed axial fans, exhaust ventilation, and to develop security measures.
Keywords:calculation of reserves; mine development; mine field divi