- 1、本文档共63页,可阅读全部内容。
- 2、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 5、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 6、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 7、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 8、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
xxxxx
地下人防工程施工方案
编制人:
审核人:
批准人:
编制单位: xxxxx 建设集团有限公司
xxxx 项目部
编制日期: 2017 年 6 月 25 日
地下人防工程施工方案
地下人防工程施工方案
目 录
1. 编制依据 1
2. 工程概况 1
3. 施工准备 3
3.1 施工现场准备 ······························································· 3·
3.2 施工流水段划分原则 ······················································ 3·
3.3 施工流程 ····································································· 3·
4. 技术准备 3
5. 材料准备 4
5.1 钢筋原材 ····································································· 4·
5.2 模板架料 ····································································· 6·
5.3 混凝土 ········································································ 6·
6. 机具准备和劳动力安排 7
6.1 机具准备(人防部分) ··················································· 7·
6.2 劳动力安排(人防部分) ················································ 7·
7. 主要的施工方法和技术措施 8
7.1 钢筋工程 ····································································· 8·
7.2 模板工程 ····································································3·1
7.3 混凝土工程 ·································································4·1
8. 质量保证措施 51
8.1 钢筋工程质量控制 ························································5·1
8.2 模板工程质量控制 ························································5·1
8.3 混凝土施工质量控制措施 ···············································5·3
9. 成品保护措施 54
10. 安全生产与文明施工措施 555
地下人防工程施工方案
1. 编制依据
《混凝土结构施工图平面整体表示方法制图规则和构造详图筏形基础》
16G101-3
《混凝土结构施工图平面整体表示方法制图规则和构造详图》