《工程项目管理》英文课件第7章 Scheduling Techniques .ppt

《工程项目管理》英文课件第7章 Scheduling Techniques .ppt

7.4 Crashing and Time/Cost Tradeoffs 60 Assigning more workers to a particular activity will normally result in a shorter duration. Greater speed may result in higher costs and lower quality, however. In this section, we shall consider the impacts of time, cost and quality tradeoffs in activity durations. 7.4 Crashing and Time/Cost Tradeoffs 61 Considering only this activity in isolation and without reference to the project completion deadline, it would undoubtedly choose a duration which implies minimum direct cost, represented Cij . At the other extreme, it might choose to

文档评论(0)

1亿VIP精品文档

相关文档