OUTER CIRCULAR HIGHWAY TO THE CITY OF COLOMBO (Southern Section) (STA17+500~STA28+500) Method Statement for the Construction of Pier and Pier cap for Viaduct (Revision 2) CHINA HARBOUR ENGINEERING COMPANY LTD. 13th January 2011 Content TOC \o 1-3 \h \z \u 1.0 Purpose of Method Statement 3 2.0 Scope of this method statement 3 3.0 Documents to be referred with this Method Statement 3 4.0 Responsibilities for activity Describe within this Method Statement 3 5.0 Detailed Method and Procedures for carrying out this Method Statement 1 5.1 Material 1 5.2 Equipment 1 5.3 Method of constructio