采暖工程 施工方案
工程名称:楼
施工单位:
编制日期: 2014 年 8 月 2 日
目 录
一 施工准备计划 ····························································· 2·
二 工程概况 ··································································· 2·
三 施工程序与施工方法 ···················································· 2·
1、安装准备 ···································································· 2·
2、主管道安装 ································································· 3·
3、地热管安装 ································································· 3·
4、散热器安装 ································································· 6·
5、水压试验 ···································································· 7·
6、管道冲洗 ···································································· 7·
7、通暖 ·········································································· 7·
四 保证质量技术措施 ························································ 8·
五 保证安全文明施工的技术措施 ········································· 8·
六 保证工期技术措施 ························································ 9·
七 成品保护措施 ······························································ 9·
八 多工种施工配合措施 ·····················································10
一 施工准备计划
1 接到图纸后认真看图,审图,做好图纸审前准备工作:
2 按图纸提出材料计划,材料员搞好市场调查:
3 组织施工人员进行培训,做好技术交底工作:
4 做好机具设备检修工作,准备足够的人力,物力进行施工,准保工程期按时
完成。
二 工程概况
本工程为公司建设的工程。本工程设计使用年限 50 年,工程等级为二级,
总建筑面积:4032 ㎡,建筑层数六层, 一层为框架商服, 二~六层为砖混住宅,
一层层高 3.6 米,二~六层层高2 .9 米,建筑总高度 21.10 米,建筑总长度
49.34m,建筑总宽度 13.49m,结构形式为底部框架结构上部砖混结构,建筑
耐火等级二级,屋面防水等级二级,抗震设防烈度六度。
三 施工程序与施工方法
本工程主管道采用焊接钢管,分户采用地面辐射采暖系统,散热