- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
新桥道口安装整体道口板
施工组织设计
永煤公司铁路运输处
目??录
1工程施工模式·········································································2
2安装整体道口板工程施工方案···············································2
2.1整体道口板施工人员组织···················································2
2.2整体道口板施工布置平面图···············································3
2.3整体道口板施工··································································3
2.4施工前准备工作···································································3
2.4.1作业准备···········································································4
2.4.2技术准备···········································································5
2.5材料、机具等摆放位置·························································7
2.6整体道口板铺设纵断面图···················································8
2.7整体道口板铺设施工流程···················································9
2.8铁路验收开通·····································································10
3、施工安全措施·······································································10
3.1铁路方向安全防护·····························································10
3.2公路方向安全防护措施·····················································11
3.3施工现场安全防护措施·····················································11
4施工所需机具、材料·····························································12
4.1所需机具、工器具······························································12
4.2修所需材料··········································································13
新桥道口安装整体道口板施工组织设计
1工程施工模式
1.1新桥道口属于新桥矿地销公路道口,位于新桥矿铁路专用线DK6+273.4处,现为木枕式橡胶道口板铺面,公路路面宽度12米,公路与铁路为平交,平交道口宽度为12米,由于过往车辆多为拉煤车,载重量大,造成道口铺面板损坏、道口线路病害严重,危极行车安全,为了修复永涡道口破损路面,恢复道口良好状态,保证铁路行车安全,计划对该平交道口铺面进行整体式改造,由铁运处组织施工。
1.2新桥道口为50kg/m钢轨线路,计划采用购进的钢筋混凝土整体道口板和底板,现场吊装铺设,整体道口板①长度为2.5米/块,宽3米,需4块;②长度为2米/块,宽3米,需1块,合计12米,底板共预制12米,使铁路方向整体道口板下部两侧各伸出0.2米,底板下部用半干混凝土压实找平。道口两侧预埋热熔管,具体数量和位置由电务段确定。
2安装整体道口板工程施工方案
2.1整体道口板施工人员组织
施工组织领导小组
组长:张磊
施工负责人:郑伟
成员:任洪俊?李永泉?夏?飞?李亚峰
徐?强?李汉强?杜国昌?孟红光
责任分工:
张磊:负责施工管理与协调工作;
郑伟:全面负责施工现场管理工作;
任洪俊:负责施工安全管理工作;
李永泉:负责施工技
您可能关注的文档
最近下载
- 多联机空调施工组织方案.doc VIP
- 2022高三联考作文“孟子认为,人皆有恻隐之心”审题指导及优秀范文.docx VIP
- 印度世界——-美国洛杉矶郡艺术博物馆藏印度文物.pdf VIP
- 2023北京第二次高中学业水平合格性考试信息技术试卷试题(答案详解).pdf VIP
- 优迈优耐德扶梯IECB 扶梯控制柜-调试指导书.pdf
- 地砖铺贴施工方案与技术措施.docx VIP
- 多联机空调施工方案2.docx VIP
- 财务会计-开票加税点.xlsx VIP
- 内科院感工作计划科室院感度工作计划.docx VIP
- 2025课件-GB46768-2025有限空间作业安全技术规范PPT解读-新版.pptx
原创力文档


文档评论(0)