南沙人才公寓(南慧湾)项目土方开挖回填施工方案

目录

一、编制依据·······························································································2·

二、工程概况·······························································································2·

三、基坑内土层及地下水情况··············································································3·

四、工程特点、难点··························································································4·

五、土方开挖方案·····························································································4·

1、现场准备工作:.

2、基坑周边及基坑内排水措施.

3、基础测量定位.

4、施工人员及材料设备的准备.

5、施工用电及施工照明的准备.

六、土方回填方案····························································································15·

1、土料要求与含水量控制.

2、基底处理.

3、压实的一般要求.

4、质量控制与检验.

七、工期与工期保障措施···················································································17·

八、土方坍塌应急预案······················································································18·

1、现场可能发生坍塌事故的环节.

2、预防措施.

3、应急预案工作流程图.

4、基坑安全处理措施.

九、安全管理··································································································21·

十、文明施工··································································································21·

1

浙江宏宇建筑有限责任公司

南沙人才公寓(南慧湾)项目土方开挖回填施工方案

一、编制依据

1、南沙人才公寓(南慧湾)项目《施工组织设计》;

南沙人才公寓(南慧湾)项目工程施工总平面布置图;

南沙人才公寓(南慧湾)项目设计文件;

南沙人才公寓(南慧湾)项目《地质勘察报告书》;

5、《建筑工程质量验文件收统一标准》(GB50300—2001);

6、《建筑地基基础施工质量验收规范》(GB50202—2002);

7、《建筑施工安全检查标准》(JGJ59—2012);

8、《施工现场临时用电安全技术规范》(JGJ46—2005);

9、《建筑机械使用安全技术规范》(JGJ33—2012);

二、工程概况

本工程位于广东省广州市南沙区南沙街资讯科技园安捷利地块南侧,

工程由广东建筑艺术设计院有限公司设计,广东省重工建筑设计研究院有

限公司地质勘察,广州建筑工程监理有限公司监理,浙江宏宇建筑有限责

任公司总