SECTION13

ELASTOMERICBEARINGS

SECTION13-ELASTOMERIC

BEARINGS

CONTENTS

CLAUSENUMBERPAGE

13.1ELASTOMERICBEARINGSS13-1

13.2SAMPLING,TESTINGANDACCEPTANCES13-1

13.3INSTALLATIONS13-3

13.4EPOXYMORTARS13-3

13.1ELASTOMERICBEARINGS

1.General

1.Elastomericbearingsshallbemanufacturedanddinaccordancewiththis

SpecificationandthedetailsontheDrawingsandshallbeinstalledatthelocationsshown

ontheDrawings.

2.ThroughoutthisSpecification,theterms,“rubberbearings”,“elasticbearing”or“bearing”

referstoabearingconsistingwhollyofrubberoroneormorevulcanizedrubberslabs

bondedtometaltestoformasandwicharrangement.

2.TypeApproval

1.ManufactureofbearingshallnotcommenceuntiltheSubcontractorhasreceived

preliminaryapprovalofthattypeofbearinginwritingfromtheSubcontractororhis

Representative.

2.Atleast30dayspriortocommencingmanufacturetheSubcontractorshallsubmittothe

MainContractororhisRepresentativeforapprovalthedesigndetailsandcalculationsof

thebearings.Heshallincludeanyrelevantinformationconcerningthemethodsand

materialsheproposestouseforthebearinginstallation.

3.制造

根据第3.12条成功完成型式试验后,分包商应提交制造计划建议。

本计划应确保支座在分包商预计安装时间之前充分准备好。应预留时间进行验收测试,

以及在支座失败时制造和测试替代支座的时间。

分包商还应有关质量控制的信息和he

将给主承包商或其代表检查的数据。每个支座应在模制过程中通过压印

永久标记以下信息:1.项目名称2.制造商名称3.制造日期4.序列号5.制造商证

书6.保修7.主承包商或其代表指示的其他识别标志,例如承载能力、类型。

13.2抽样、测试和验收

测试频率

1.为了取样、测试和验收的目的,一批次应由同一尺寸和设计的支座组成。批次的

大小应反映生产批次的大小,并应由分包商与主承包商或其代表协商确定,但任何

一批次超过100个支座。

程序

2.在分包商准备开始安装支座前至少3个月,且在交付现场之前,他应请求主承包商

或其代表,根据第3.12条的规定对成品支座进行取样和测试。

取样

3.Manufac