石家庄经济学院
本科生毕业论文
外文翻译
题 目 国际建设工程风险分析
姓 名 刘子豪
学 号 510105020109
学 院 管理科学与工程
专 业 工程管理
指导教师 孙卫东
2012年4月25日Risk Analysis of the International Construction Project
ABSTRACT
This analysis used a case study methodology to analyse the issues surrounding the partial collapse of the roof of a building housing the headquarters of the Standards Association of Zimbabwe (SAZ). In particular, it examined the prior roles played by the team of construction professionals. The analysis revealed that the SAZ’s traditional construction project was generally characterized by high risk. There was a clear indication of the failure of a contractor and architects in preventing and/or mitigating potential construction problems as alleged by the plaintiff. It was reasonable to conclude that between them the defects should have been detected earlier and rectified in good time before the partial roof failure. It appeared justified for the plaintiff to have brought a negligence claim against both the contractor and the architects. The risk analysis facilitated, through its multi-dimensional approach to a critical examination of a construction problem, the identification of an effective risk management strategy for future construction projects. It further served to emphasize the point that clients are becoming more demanding, more discerning, and less willing to accept risk without recompense. Clients do not want surprise, and are more likely to engage in litigation when things go wrong.
KEY WORDS Arbitration claims construction contracts litigation project and risk
The structural design of the reinforced concrete elements was done by consulting engineers Knight Piesold (KP). Quantity surveying services were provided by Hawkins, Leshnick Bath (HLB). The contract was awarded to Central African Building Corporation (CABCO) who was also responsible for the provisi