本科毕业设计(论文)
西南某医学院住院大楼
CFG复合地基与筏形基础设计
摘 要
随着经济的发展与人们居住环境要求的提高,近年来我国建筑、市政等工程得到飞速发展。在都市中,寸土寸金,因而在建筑向高空发展的同时,地下空间的利用也成为一个重要方向。高层及多层建筑的地下室、地下商场、地下车库等工程施工,都会面临地基基础工程和深基坑工程。
该建筑总建筑面积约为28000m2,建筑物高度为69.3m,其层数为20层,设有地下室一层,埋深约-4.5m,框剪结构,建筑物安全等级为Ι级,单柱最大荷载为1400T。该设计是典型的地基基础与深基坑相结合的工程设计:首先,对施工现场进行详细的地质勘探,对其结果进行严密的勘察分析,得出地堪报告;其次,根据地勘
关键词 基础设计;筏板基础;CFG桩;基坑支护
Abstract
In recently years, with the rapid development of the economy and the improvement of peoples living environment, the project of building and municipal engineering got a rapid development too.In the big city, inch of land inches of gold,so at the same time of the con- struction to high altitude, underground space is becoming an important aspect too. All that of higher level and tier building basement,underground market, underground garage engin- neering construction will be confronted with foundation work and deep foundation engine- ering.
The total construction area is about 28000m2. The height of the building is 69.3m.Its a 20-floor building with one floor of basement. The setting depth is -4.5m.Its a frame-shear wall structure. The safe grade of this building is I. Single column peak load is 1400T. This is a typical design which is combined with foundation and deep foundation.At first,they proceed detailed geologic exploration to the job location;Secondly,from the geology report which offered correlated data,we can proceed foundation design. Because constructional topside load is quite big and the geologic condition is comparatively good ,so I used raft foundation. In consideration of construction period and difficult-easy degree,I used flatbed raft foundation.Raft board is designed by the JCCAD procedure in software PKPM, at the end we could directly obtain distributed steel diagram and distributed steel map measurement. But owning to natural bearing course is insatiable design requirements,so the foundation should be disposed,the design choose CFG pile to dispose the foundation,then bearing capacity