4.8.2 MECHANICAL WORK 4.8.2.1 Cleaning During and After Erection EQUIPMENT AND PIPING The Bidder shall ensure that all mechanical equipment erected by him is kept clean during and after erection. The Bidder shall submit the procedure of piping cleaning for owner reviewed and approval. CUTINS AND OPENINGS The Bidder shall clean out the inside of all cut ins and openings made by him in the piping for new connections. The Bidder shall blow out the piping prior to making new connections, if required. CLOSURES All openings shall be provided with temporary closures, as so