污水施工组织设计
副本
遵义市北部污水处理厂管网配套(高坪镇—董公寺小岛渔村段)土建工程
(项目名称) 三 标段施工招标
投 标 文 件
投 标 文 件 内 容: 技术标
投 标 人: (盖单位章)
法定代表人或委托代理人: (签字或盖章)
日 期: 2010 年 6 月 2 日
目 录
一、 施工方案与技术措施·······································································1
二、 质量保证措施和创优计划·····························································16
三、 施工总进度计划及保证措施·························································20
四、 施工安全措施计划·········································································22
五、 文明施工措施·················································································27
六、 施工场地治安保卫管理计划·························································30
七、 施工环保措施计············································································33
八、冬季和雨季施工方案·······································································35
九、 施工现场总平面布置·····································································37
十、 现场组织管理机构·········································································39
十一、与发包人、监理及设计单位、专业分包工程的配合················52一、 主要施工方案及技术措施
(一)施工测量的要求
1.施工测量必须符合施工图纸及《工程测量规范》的有关要求。
2.对建设单位提供的控制点,在复核无误、精度符合要求后方可引用。
3.场区内按施工情况需要增设水准点,测量精度按不低与二等水准测量精度进行测
(二)施工测量的组织
组建以3 名测量工程师和4 名测量工组成的测量小组,对整个工程进行全过程的跟踪测量。控制点的复核和控制网的建立阶段4 人,其中仪器操作1 人,投点1 人,现场记录、内业整理2 人,平面轴线定位、放线阶段4人。由于本工程结构复杂工期很紧,考虑到分段施工的总体部署,当施工繁忙时,可再将人员一分为二,三人为一组进行工作。
(三)施工测量
1、平面控制测量
根据总平面图和甲方提供的施工现场的基准控制点,用全站仪在场区按相当于二级导线精度要求进行两测回的测角、测距,联测的数据精度满足测量规范的要求后,即将其作为本工程布设平面控制网的基准点和起算数据。
2、工程定位放线
根据设计图纸,计算待测点坐标,应用激光经纬仪的坐标放样模式进行放样,放样点必须进行复核。激光经纬仪坐标放样示意图
(四)施工测量的措施
(1) 建立测量组,专人观测和成果整理。
(2) 仪器和工具按照规定的日期、方法及专门检测单位进行标定。
(3) 加强对测量用所有控制点的保护,防止移动和破坏;一旦发生移动和破坏,立即报告监理,并协商补救措施。
(4) 所有测量成果及时提出成果报告提供给监理检测审批。
(五)施工监测
1、监控量测目的与意义
为了确保工程稳定性。成立专门的监测管理小组,建立监控量测系统,随时反馈信息,施行信息化施工,为工程顺利地施工提供科学依据。
2、监控量测的施工组织
组长由项目经理兼任,总工程师任副组长,成立现场监控量测管理小组。下设观测、数据处理、信息反馈三个专业组。专业组长为监控测量工程师。每个专业组设组员两名。
3、监控量测的基本要求
⑴监测组织要有严