南茅运河航运建设危桥改造工程 红旗桥 (35+58+35)m预应力连续刚构 边跨现浇段专项施工方案 (班咀桥、文明桥边跨现浇段施工方案参照本专项施工方案) 湖南大胜集团南县工程项目管理部 二0一五年八月十一日 目 录 一、编制说明············································1 二、工程概况············································2 三、施工进度············································2 四、资源配置计划 ································· 4 五、施工工艺要求········································10 六、安全保证措施········································11 七、质量保证体系········································12 八、施工方案设计图(附图1、2、3、4) 编制说明 1.1南茅运河航运建设三座危桥改造工程上部结构边跨现浇段原设计施工方案为采用满堂支架施工,根据现场实际情况,桥梁边跨现浇段长7米,有3.12