* Schedule Plan Compiling (CMP) Forward Pass Calculate the earliest dates at which activities may commence(开始) and the project be completed Backward Pass Calculate the latest start dates for activities * Schedule Plan Compiling (CMP) Forward Pass An example project specification with estimated activity durations and precedence(优先) requirements Activity No Duration Precedents A B C D E F G H Description Hardware Selection Software Design Install Hardware Code Test File Take-on (收集) Write user manual User Training Install Test system 6 4 3 4 3 10 3 A 2 B B E,F C,D * Schedule Plan Compiling