Risk analysis (ii) Risk planning Consider each risk and develop a strategy to manage that risk. Avoidance strategies The probability that the risk will arise is reduced; Minimisation strategies The impact of the risk on the project or product will be reduced; Contingency plans If the risk arises, contingency plans are plans to deal with that risk; Risk management strategies (i) Risk management strategies (ii) Risk monitoring Assess each identified risks regularly to decide whether or not it is becoming less or more probable. Also assess whether the effects of the risk have changed. Each key ri