HydromechanicalanalysisofPlacingandprotectingfill(坝体填料的填筑保护及基础流体力学行为分析)
Hydromechanical analysis of Placing and protecting fill
flow behavior in dam
Frist Placing and protecting fill
Fill shall be placed so that mo part of the final foundation surface remains exposed for more than 72 hours.
Fill shall be placed in such methods as will prevent segregation of the material.
Where the Contract requires the placing of different types of fill in separate zones,the Contractor shall carry out the work so as to prebent mixing of different types of fill.Shoud there be ,in the opinion of the Engineer, any excessive mixing of different types of fill , such mixed materials shall be removed to a spoil tip and replaced with fresh fill.
Any undesirable material accumulated on the fill surface shall be removed before placeing the next layer of fill.No fill material shall be placed on a previous layer of that has dried out,become saturated or in any way deteriorated by exposure or by spilling of other material or disterbance by mechanical transport or by deposition of wind blown particles or by any other means. Before fresh fill material is placed aoo such deteriorated fill or foreign material shall be removed to a depth at which material of an acceptable standard is exposed. The surface of each layer is to be approved by the Engineer before the next layer is placed.
Any fill shall be placed in uniform layers not greater than the approved thickness as specified hereafter and in an orderly sequence approximately horizontal along the centreline of the embankments.Except where specified of directed otherwise, no portion of any embankment shall be stepped more than 3 feet higher than any immediately adjacent portion except where permitted by the Engineer and the slope formed by such steps shall not exceed 1V:3H and not less than 1V:4H from one level to another.Except as shown on the Drawings or as otherwise directed, all fill placement surfaces shall be sloped at right angles to the centerline of the embankment in both the upstream and downstream di
您可能关注的文档
最近下载
- 2025年日照市中考生物试题卷(含答案).docx
- 征信报告模板-带水印版.docx VIP
- 钢筋混凝土化粪池22S702.docx VIP
- 标准图集-20S515-钢筋混凝土及砖砌排水检查井.pdf VIP
- 文广旅体局三防应急预案.docx
- 第3讲 秦统一多民族封建国家的建立课件—2024届高三历史统编版一轮复习.pptx VIP
- 第1讲 先秦:统一多民族封建国家的奠基时期 课件--2024届高三统编版(2019)历史二轮专题复习.pptx VIP
- 第一讲 中华文明的起源与奠基——先秦时期(远古—公元前221年)+课件+---2025届高三历史统编版二轮通史复习.pptx VIP
- 2025年潍坊市中考生物试题卷(含答案逐题解析).docx
- 2025年中国AI眼底筛查设备市场调研报告_2025年12月.docx VIP
原创力文档

文档评论(0)