高速公路长安隧洞身开挖、支护方案大学学位论文
申嘉湖高速公路湖州鹿山至安吉孝源段
第3合同段
长安隧道
洞身开挖、支护方案
中交第三航务工程局有限公司
项目经理部
二0一六年五月
目 录
一、开挖················································3
1、台阶法开挖·····················································3
2、注意事项·······················································4
3、全断面开挖·····················································9
4、仰拱开挖························································12
5、中心水沟·······················································16
6、超欠挖处理·····················································20
二、超前支护············································20
1、超前小导管······················································20
2、φ25超前全长粘结型锚杆········································22
三、初期支护············································22
1、钢架···························································22
2、钢筋网·························································23
3、钢筋网铺设······················································26
4、锚杆施工·······················································26
5、喷射混凝土施工·················································31
6、超前地质预报···················································34
四、安全、质量措施······································39
1、爆破作业安全措施及应急办法·····································39
2、爆破施工应急措施···············································40
3、爆破安全技术····················································40
4、炮烟及盲炮的预防················································41
5、工程质量检查验收程序···········································42
6、质量保证体系···················································43
7、安全保证体系····················································47
洞身开挖、支护方案
申嘉湖高速公路第3合同段长安隧道所处地层地质复杂,表层断续覆盖第四系残坡积(Qcl+dl)碎石孔隙潜水含水层,厚度小,且多处于地下水常水位以上,降雨时充水,雨后排泄,总体水量贫乏,根据围岩级别和设计要求并结合现场实际地质情况,采用相应的开挖方法:洞口段采用台阶法预留核心土开挖、Ⅳ级、Ⅴ级围岩一般地段采用台阶法开挖、Ⅲ级围岩地段采用全断面法开挖。
一、开挖
1、台阶法开挖
施工原则:
⑴、避免对原地层扰动。
⑵、台阶推进,机械配合人工开挖,必要时采用弱爆破。
⑶、开挖化大为小,支护宁强勿弱。
⑷、轮廓稍大勿小,及早封闭成环。
⑸、稳扎稳打,岩变我变。
洞身开挖采用台阶法预留核心土开挖施工,在隧道开挖过程中,在三个台阶上分七个开挖面,以前后七个不同的位置相互错开同时开挖,然后分部同时支护,形成支护整体,缩短作业循环时间,逐步向纵深推进,形成开挖及初期支护,仰拱紧跟
您可能关注的文档
- 电子商务物流管理课程实践论文大学学位论文.doc
- 电子设备的防震设计 大学学位论文.doc
- 电子商务让地毯绣秀出风采 大学学位论文.doc
- 电子实时钟 课程设计任务书(硬件)大学学位论文.doc
- 电子商务园区建设 大学学位论文.doc
- 电子有限公司创业计划书大学学位论文.doc
- 电子元器件的选择与应用大学学位论文.doc
- 电子杂志《在路上》创业策划书 大学学位论文.doc
- 电子系统设计与实践论文范例 大学学位论文.doc
- 电子政务与运行的思考和创新论文大学学位论文.doc
- 福莱特玻璃集团股份有限公司海外监管公告 - 福莱特玻璃集团股份有限公司2024年度环境、社会及管治报告.pdf
- 广哈通信:2024年度环境、社会及治理(ESG)报告.pdf
- 招商证券股份有限公司招商证券2024年度环境、社会及管治报告.pdf
- 宏信建设发展有限公司2024 可持续发展暨环境、社会及管治(ESG)报告.pdf
- 品创控股有限公司环境、社会及管治报告 2024.pdf
- 中信建投证券股份有限公司2024可持续发展暨环境、社会及管治报告.pdf
- 洛阳栾川钼业集团股份有限公司环境、社会及管治报告.pdf
- 361度国际有限公司二零二四年环境、社会及管治报告.pdf
- 中国神华能源股份有限公司2024年度环境、社会及管治报告.pdf
- 广西能源:2024年环境、社会及治理(ESG)报告.pdf
文档评论(0)