- 19
- 0
- 约2.53万字
- 约 76页
- 2017-05-13 发布于广东
- 举报
9国际工程合同条件的理解与运用5
第一节 国际工程合同中的风险承担 ICE:Adverse physical conditions and artificial obstructions 12 (1) If during the execution of the Works the Contractor shall encounter physical conditions (other than weather conditions or conditions due to weather conditions) or artificial obstructions which conditions or obstructions could not in his opinion reasonably have been foreseen by an experienced contractor the Contractor shall as early as practicable give written notice thereof to the Engineer. 第一节 国际工程合同中的风险承担 ICE:Intention to claim (2) If in addition the Contractor intends to make any claim for additional payme
原创力文档

文档评论(0)