桥梁工程课程设计全英文

Chapter I the original design dataA three-span simply supported beam bridge, using column pier piles, U-shaped abutment. 1. Bridge clearance Bridge clearance: 11 +2 × 0.75m 2. And the total length of the girder span Standard span: 20.00 (pier center distance); Calculated span: 19.50 (bearing center distance); Main Beam Length: 19.96 (main beam prefabricated length). 3. Design load Road-I level loads, the crowd 3.5kN / m 4. Material Main Beam: Concrete C40, bulk density 26kN/m3 5. Structure size 12.5m wide bridge using five beams, precast beam height 1.7m, width of the bridge girder spacing st