- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
国家工期定额解读案例(国外英文资料)
国家工期定额解读案例(国外英文资料)
Application and interpretation of the provisions of the state construction quota
First of all, the article 4 of the relevant provisions of the national 2000 industrial standard:
4 at the same time a contractor contracts for more than two (2) item (a) project, the construction period of computing: with a maximum time limit for a project of the single item (a) engineering base, plus other single sum (a) construction period by corresponding coefficient calculation: add a multiply 0.35 coefficient; Plus 2 times the 0.2 coefficient; Plus 3 times 0.15; More than four single items (bits) are not added to the construction period.
In the real work, people often ask this question, in order to facilitate the intuitive understanding of the meaning of this article, in this case, the application is interpreted, for example:
A bid tendering: frame shear wall structure, goods small high-rise residential buildings (in this case interpretation does not consider the basement and foundation engineering), 1 #, 2 #, 3 #, 4 #, 5 #, 6 #, 7 #, 8 # of eight single items of projects as a block, according to every single items of projects as a cornice height and building area, 2000 national construction norm, get the corresponding period fixed number is as follows:
# 1, 320 days, 2 # building blocks 280 days, 3 # 3 buildings 310 days, 4 # building 360 days, 5 # building 290 days, 6 # building 380 days, 7 # building 250 days, 8 # building 260 days
From these correspond to the size of the fixed time limit for a project, combined with the provisions of national construction norm, we determine the fixed time limit for a project in bidding, should take 380 days of 6 # building, to base the rest of the fixed time limit for a project shall be carried out in accordance with the provisions of accumulative multiplied by the coefficient to calculate.
Before the calculated period, also consider the location of the project provinces of the adjustment coefficient of fixed time limit for