压力管道设计设计人员考试卷2006(国外英语资料)
压力管道设计设计人员考试卷2006
This article is contributed by rgsmdqy
Pdf documents may experience poor browsing on the WAP side. It is recommended that you first select TXT, or download the source file to the local view.
In 2006, the pressure piping designers checked the papers
Full name:
Company:
Grade:
I. judgment questions (1 points per subject, 20 points each)
1., fire furnace, auxiliary fuel gas tank, fuel gas heater and furnace body P7, 3.7.7) (x) fire spacing shall not be less than 7.5m. (SH3011 2.
The combustible liquid pump with operating temperature equal to or higher than the autoignition point shall be centrally arranged and operated
A fire-resistant liquid pump with a temperature below the autoignition point shall have a fire interval of not less than 7.5m; there shall be a 4.5m fire interval between the liquid and the LPG pump. (SH3011, 3., P8, 3.10.12) (x)
The tower and vertical containers arranged along the main corridor, such as the top of the corridor without equipment, can be distributed
Located on both sides of the main corridor; if there is equipment above the main corridor, the site or passageway of the equipment above the corridor shall be reserved on the side of the main corridor. (SH3011 4. P4 3.2.3) (V)
Platforms and ladders shall be provided where operations are required and regular maintenance shall be maintained. Press P12.4.3.1 (SH3011) (*)
Safety ladder is required. Five
Transmission medium has special requirements and the straight pipe 2.0.11 on the distance and angle of elevation, etc.) (V)
The layout of the piping shall be in accordance with the requirements of the equipment layout. (H3012 P2 6.
The buried depth of buried pipeline should be based on the principle that the pipeline is not damaged and should be tested
The maximum frozen soil depth and groundwater table are considered. The distance between the pipe top and the ground should not be less than 800mm; (500mm) there is the area of concrete ground outside, and the pipe top is not less t
您可能关注的文档
最近下载
- 项目可行性研究报告大纲.pptx VIP
- 小学体育五年级下册教案(最全).doc VIP
- 照顾老人保姆合同范本10篇.docx VIP
- 图形推理专项练习题.FIT).pdf VIP
- 《钢轨超声波探伤系统的设计》【毕业设计论文】.doc VIP
- 2022年广东高考生物试卷真题及答案详解(精校版).pdf VIP
- Panasonic 松下 录像机 DMR-EH59 DMR-EH49 Operating Instructions 操作手册说明书 (英语).pdf
- 迪罗—特马法纤维开松混合设备机械原理.pdf VIP
- 高考英语单词3500乱序版.pdf VIP
- 2024年新课标高考福建高考真题生物试卷(原卷版).docx VIP
原创力文档

文档评论(0)