分部分项工程的划分(国外英文资料)
分部分项工程的划分
Construction and installation of quality inspection and assessment of the sub - division, division, unit division of the project
In order to facilitate the supervision and inspection of the quality of the project, control the quality of the process, the quality of the parts and ensure the quality of the unit project, the quality of the construction and erection works shall be divided into the items, the parts and the units, and the quality shall be examined and evaluated.
(1) division of sub projects;
1. generally divided according to the main types of work. For example, masonry construction, masonry, steel engineering, concrete engineering, paint engineering, glass engineering, plastering engineering etc.;
2., multi-storey or high-rise housing projects in the main sub division projects, the floor must be divided into sub projects;
3. single storey housing in the main part of the project, according to the deformation of the seam or axis of sub projects;
4. in addition to the main sub division of the project by the floor or deformation division of sub projects, a total of his sub works may also be divided into sections of sub projects. But it is difficult to divide the project with smaller amount of work or to divide the floor according to the floor. Any sub works included in the evaluation of each sub project shall be assessed.
(two) division of divisional works;
1. engineering division is the main parts of buildings or structures division, such as, foundation and foundation engineering, the main part of the project, ground and floor engineering, and engineering, decoration engineering, roof engineering, construction six engineering division.
For the basement project, in addition to + 0 structure and engineering division of waterproof part of the foundation and foundation division, other sub projects, were incorporated into the corresponding ground and floor decoration, doors and windows and other branch of Engineering in.
2. the sub project names include