国家优质工程煤矿工程现场复查要点(Key points for on-site review of national quality engineering coal mine)
国家优质工程煤矿工程现场复查要点(Key points for on-site review of national quality engineering coal mine)
Key points for on-site review of national quality engineering coal mine
I. mine construction project
project
Main review content
Data to be provided and
Physical apparent quality
Executive specifications,
standard
Vertical shaft engineering
(1) check the cross section of shaft section and vertical degree of shaft lining;
(2) check the quality of shaft lining;
(3) check the total water inflow of the shaft;
(4) to review the inspection records of concealed works, the test reports of materials and test blocks, and the quality inspection and certification materials of the project;
(5) the quality of shaft equipment.
(1) the inspection plan of vertical degree of shaft lining and the measured sectional drawing.
(2) well completion inspection records, the quality grade is good, real good perception.
(3) the total water leakage recorded in the wellbore shall not be greater than 6 tons /h.
(4) record of acceptance of concealed works, materials and test block test report.
(5) shaft equipment acceptance record, excellent quality and grade, take the cage to feel smooth fou.
(1) specifications for construction and acceptance of mine roadways in Peoples Republic of China (GBJ213-90);
(2) quality inspection and evaluation standard of Peoples Republic of China coal mine roadway engineering. (MT5009-94)
Inclined shaft engineering
Tunnel engineering
(1) wellhead portal project;
(2) well tunnel engineering;
(3) ditch project;
(4) floor and stair work.
(1) the final acceptance record and quality grade are excellent.
(2) raw material test and test block test report.
(3) the wellhead, portal concrete end wall, wing wall surface is smooth and uniform color. After no obvious wrong station, running mode, the overall outline clear, angle straight line, edge, facing slope firmly, good soil and water conservation, drainage facilities, smooth drainage, no deposit.
(4) the bottom plate is smooth and the dra
您可能关注的文档
- 华为、美能达的绩效考核秘诀(HUAWEI, Minolta performance tips).doc
- 华南植物,不全(Southern China plant, incomplete).doc
- 华南师大外文学院真题(Southern China Normal College of foreign languages.).doc
- 华佗五禽图健身法练习要领(Hua Tuo five bird figure fitness method exercise Essentials).doc
- 华南理工大学2012考研复试分数线公布(South China University of Technology 2012 postgraduate entrance examination retest scores announced).doc
- 华帝减利润 不要怪奥运(Don't blame the Olympics for Vatti's profit margins).doc
- 华附初中趣味数学题(China Junior High School Math interest).doc
- 华立集团对标胜任素质模型开发领导力(HOLLEY group benchmarking competency model development leadership).doc
- 单位发放实物福利的财税处理(Fiscal and taxation treatment of unit offering physical benefits).doc
- 卓越团队训练(Team training excellence).doc
- 2023咸阳职业技术学院招聘笔试真题参考答案详解.docx
- 2023四川化工职业技术学院招聘笔试真题及参考答案详解.docx
- 2023哈尔滨职业技术学院招聘笔试真题及参考答案详解.docx
- 2023商洛职业技术学院招聘笔试真题及答案详解1套.docx
- 2023呼伦贝尔职业技术学院招聘笔试真题参考答案详解.docx
- 2023南阳农业职业学院招聘笔试真题参考答案详解.docx
- 2023天津公安警官职业学院招聘笔试真题带答案详解.docx
- 2023年上海电机学院招聘笔试真题参考答案详解.docx
- 2023年四川艺术职业学院招聘笔试真题参考答案详解.docx
- 2023安徽体育运动职业技术学院招聘笔试真题及答案详解一套.docx
文档评论(0)