工程形象(The engineering image)
Iii. Project image progress
1. Completion of the current project schedule:
The schedule of the current schedule is the monthly progress plan of the phase ii expansion project of the company
Compare the benchmark with the actual progress. The comparison results are shown in the table below
Project completion planning degree (%)
Civil engineering
The main plant 13 meter column concrete pouring part complete 25 %
2. The concrete pouring of 10.98 meters of floor beams of the main plant is not 0 %
3. The bottom plate of coal pit is poured 100%
The masonry section of the chimney shall be 80 %
5. The excavation and bedding of the clay excavation are 60%
The foundation of coal wall foundation excavation is 40% completed
The installation
1. The installation of the air preheater connected to the furnace is 100%
2. The installation and completion of the import and export frame of the cyclone tube is 100%
3. The boiler group of the furnace is 90% of the installation part
The water test part of the furnace is 90%
2. The analysis and measures taken for the completion of the situation, as well as the views planned for next month:
The problem of construction progress is still the main contradiction of this project. The owner proposed the three unshakable namely the determination to realize heating for the year of November 30 this year. The determination to generate electricity in the first quarter of next year will not be shaken; Carry out the heating contract with the customer. All work should be carried out around this central goal. However, the current monthly schedule provided by the company is not satisfied with the overall target of the trial run on November 30.
There are three main reasons for not completing this months plan
In the autumn harvest season, construction manpower shortage.
(2) without consent of the manufacturer, installation unit without authorization before the main steam valve of the boiler body with an elbow, manufacturers to incr
您可能关注的文档
- 巴氏奶与普通奶的区别(The difference between buttermilk and regular milk).doc
- 巴勒斯坦旅游旅行攻略(Travel guide to Palestine).doc
- 帮你认字(To help you read).doc
- 巴西ncm 号码(Brazil NCM number).doc
- 帮助我们祛湿的食物(Help us eat clearing damp).doc
- 布法罗旅游指南 (buffalo guide) - 纽约州出境游指南 yododo 游多多(Buffalo guide - New York state travel guide yododo Tours).doc
- 布料机在水泥混凝土路面摊铺施工中的应用_石磊(Application of cloth machine in cement concrete pavement paving construction).doc
- 布料基本知识(Fabric basics).doc
- 布鲁氏菌病防治技术规范(Technical specification for brucellosis).doc
- 布什在林肯号航空母舰上的讲话(Bush's speech on the uss Abraham Lincoln).doc
文档评论(0)