南开大学 13春学期《工程施工》在线作业(Nankai university 13 spring semester project construction online homework) 13 spring semester project construction online homework 1. Known work P has a tight after G, G to work at the latest finish time for 14 days, lasts for 3 days, the total time is 2 days P work for 6 days, the earliest start time duration for l days, then P work of free time for the () day 1 A. 2 B. 3 C. 4 D. A: B full score: 2 points: 2 2. In the network plan, total H working time for 3 days, there are three tight work after H J, K, L, J the earliest starting time of work and the latest starting time