DELAY ANALYSIS FOR CONSTRUCTION (施工延误分析)
DELAY ANALYSIS FOR CONSTRUCTION PROJECTS:
CLASSIFICATION OF EXISTING METHODS
by Alena VASILYEVA-LYULINA **
1. Introduction
Delay is one of the common and typical problems in construction projects. In the study of Assaf and Al-Hejji (2006) 1)
construction delay was defined as “the time overrun either beyond completion date specified in a contract, or beyond
the date that the parties agreed upon for delivery of a project”. In the United Kingdom, a 2001 report by the National
Audit Office, entitled “Modernising Construction,” revealed that 70% of the projects undertaken by government
departments and agencies were delivered late (Lowsley and Linnett 2006)2). Assaf and Al-Hejji (2006) 1) did a survey on
time performance of different types of construction projects in Saudi Arabia ran into the same conclusion (45 out of 76
projects were delayed). A study conducted by the Infrastructure and Project Monitoring Division of the Ministry of
Statistics and Programme Implementation in 2004 in India reported that of 646 central sector projects, costing about
$50 trillion (U.S. dollars), approximately 40% were behind schedule, with delays ranging from 1 to 252 months (Iyer
and Jha 2006)3).
To recover the damage caused by delays, both the delays and the parties responsible for them should be identified.
However, delay situations are complex in nature because multiple delays can occur concurrently and can be caused by
more than one party, or by none of the principal parties (force majeure, etc.). As a result contract schedule and payment
dispute are becoming two most common items of dispute during the construction phase.
2. Types of Delay
Construction project delays can be classified according to their origin into four g
您可能关注的文档
- COMPUTED TOMOGRAPHY IN THE (计算机断层扫描的).pdf
- Computation Fluid Dynamics University of (计算流体动力学大学).pdf
- Computer validation Guide Final draft objectives(电脑验证指南最终稿的目标).pdf
- Computer Simulation and Analysis of High (计算机仿真和分析的高).pdf
- Computer Programming User’s Guide Toro(计算机编程的用户指南托罗).pdf
- concept inventory fluid mechanics Bing My (库存流体力学概念必应我).pdf
- Computer) Programming) inKeyStage3) (计算机编程)inKeyStage3)).pdf
- CONCEPT AND OPERATION MODE OF THE (概念和操作模式).pdf
- ConceptDevelopment 51 Practice Page(ConceptDevelopment 51页练习).pdf
- Concept of Laser Fusion Power Plant Based on (激光核聚变发电厂的基础上的概念).pdf
- 2025届衡阳市第八中学高三一诊考试物理试卷含解析.doc
- 2025届湖南省娄底市双峰一中等五校重点中学高三第二次诊断性检测物理试卷含解析.doc
- 天水市第一中学2025届高三第二次联考物理试卷含解析.doc
- 2025届金华市重点中学高三考前热身物理试卷含解析.doc
- 2025届北京市石景山区第九中学高三第四次模拟考试物理试卷含解析.doc
- 江苏扬州市2025届高三第一次模拟考试物理试卷含解析.doc
- 2025届江苏省南通市高级中学高考物理五模试卷含解析.doc
- 广东省清远市华侨中学2025届高三第一次调研测试物理试卷含解析.doc
- 辽宁省凤城市2025届高三第五次模拟考试物理试卷含解析.doc
- 内蒙古巴彦淖尔市重点中学2025届高考仿真卷物理试卷含解析.doc
文档评论(0)