大工14春《水电站建筑物》在线测试2(Great worker, 14 spring, building of hydropower station online test 2)
大工14春《水电站建筑物》在线测试2(Great worker, 14 spring, building of hydropower station online test 2)
Great worker, 14 spring, building of hydropower station online test 2
Multiple-choice questions
I. judgment questions (10 questions, 30 points altogether)
1. judge whether the concrete cracks through, generally use the radius of concrete cracking area and concrete radius ratio to judge.
A. error
B. correct
Developing options: B
2. in the inlet way of the pressure front tank, the vertical flow is easy to occur in the forward water inlet, so the unit is not treated evenly. Therefore, the general field adopts lateral inflow.
A. error
B. correct
Developing options: A
3. general desilting basin should have the necessary cleaning works facilities, or mechanical cleaning sand, sand or water.
A. error
B. correct
Developing options: B
4. the main function of the air vent in the water intake of the hydropower station is to exhaust the water when the water diversion channel is filled. The emergency gate is closed urgently and emptying the channel to supplement the air in order to prevent the occurrence of harmful vacuum.
A. error
B. correct
Developing options: B
5. of the two rivers flow energy in section difference, because the gap between the two section and the kinetic energy of head difference is very small, can use the differential pressure head of two section between the two units to represent the energy difference between the weight of water surface.
A. error
B. correct
Developing options: A
6. the water diversion tunnel is generally affected by the freezing, and the water quality along the route is easy to be polluted.
A. error
B. correct
Developing options: A
7. dam back pipe, its pipe wall to bear all the internal pressure, the general wall thickness is relatively large.
A. error
B. correct
Developing options: B
8. the elastic resistance of surrounding rock is generated by surrounding rock and is a kind of active force.
A. error
B. correct
Developing options: A
9. when the water
您可能关注的文档
- 不能同时吃的食物(Food that cannot be eaten at the same time).doc
- 不能同吃的食物 食物相克与解法大全(Not to eat the same food grams of food and method Daquan).doc
- 不能随便吃的菜(Something you can't eat).doc
- 不良饮食习惯有害儿童健康(Bad eating habits are harmful to children's health).doc
- 不被多数人知道但却超好的东西(Something that is not known by most people but is superior).doc
- 不同蜂蜜的营养价值及功效(Nutritional value and efficacy of different honeys).doc
- 不要忽视身体发出的求救讯号(Don't ignore the distress signals from your body).doc
- 不要随便打吊瓶(Don't hit the bottle).doc
- 丙泊酚注射液说明书(Propofol Injection manual).doc
- 丙美卡因(Proxymetacaine).doc
文档评论(0)