17MTN MasterSchedule assessment 5月30

17” MNT Product Master Schedule Change 17” MNT Product Master Schedule Change (IBL start date : Array :5/29, Cell:6/13 case) (IBL start date : Array :5/29, Cell:6/13 case) Model:IM170E02(17”SXGA) May./25th/2006 Project Management ( PM ) K.Nakahara CEO Approval on 05/25/2006