外悬挑脚手架设计和施工探析
外悬挑脚手架设计和施工探析 摘要:现在社会发展迅速,人们的收入水平不断提高,施工中发生人员伤亡事故索赔额也越来越高。为了满足高层悬挑脚手架的搭设施工安全,减少安全事故的发生,避免和减少人员伤亡和财产损失,本文对高层悬挑脚手架的搭设进行方案设计,对悬挑脚手架的稳定性进行力学验算,并对高层悬挑脚手架的搭设施工工艺进行阐述,提出了搭设施工方法、材料要求、搭设和拆除的安全管理。
关键词: 设计验算;施工工艺;材料要求;安全管理
Abstract:Nowthe rapid development of the society, people’s incomelevels continue to improve,more and more highcasualtiesoccurredin constructionclaims.In order to meet the needs ofOverhanging Scaffoldhigherectionconstruction safety,reduce accidents,and avoid and reducecasualties and property losses,thehigh-rise cantileverscaffolddesign scheme,thestabilityof Overhanging Scaffoldmechanical calculation,and the topof overhanging scaffolderection constructionpaper, presentsasafety management ofconstruction method, material requirements,erectionanddismantling.
Key words:design;construction technology;materials; safety management
中图分类号:TU2
1.工程概况:
某大厦工程总建筑面积25000mm2,地下2层,地上24层,裙楼为四层,框架-剪力墙结构,外墙为干挂樱花红花岗岩和玻璃幕墙。
2.外部悬挑脚手架的设计:
2.1悬挑脚手架搭设方法:
外脚手架的搭设方法及力学性能同落地式双排扣件式钢管脚手架。悬挑脚手架立杆纵向间距(即工字钢间距)为1.4m,内外立杆间距1m,内立杆距墙面0.18m,大横杆步距1.8m,中间设一道防护栏杆,高1.2m,小横杆端部距墙面0.1m,脚手架底部设在悬挑钢梁上,作业层满铺竹脚手板,立杆底部设纵横向扫地杆。
剪刀撑间距8根立杆及转角处搭设,剪刀撑跨5个立杆,斜杆与地面成450--600角。
连墙件两步三跨设置,且各层外围框架柱处,均与柱子形成双道拉结。
2.2脚手架力学验算:
2.2.1 脚手架计算
脚手架高度最高处24m。立杆纵距la=1.4m,立杆横距lb=1m,立杆步距h=1.8m,连墙件为二步三跨设置。立杆截面A=4.89×102mm2,截面模量W=5.08×103mm2,回转半径i=15.8mm,惯性矩I=12.19×104mm4,档风系数ψ=0.77,基本风压值ω0=0.6kN/m2,钢材强度设计值#402;c=205N/mm2,连墙件横距lw=4.5m,连墙件纵距lh=1.8m,荷载只考虑装修荷载2kN/m2。脚手板荷载标准值为0.35kN/m2。
2.2.1.1横向水平杆抗弯强度及变形验算:
抗弯强度验算:
gk=0.35×0.7=0.245KN/m qk=2.0×0.7=1.4KN/m
MGk=gklb2[1-(a1/lb)2]/8=0.025kN#8226;m
MQk=qklb2/8=0.175 kN#8226;m
Max=1.2MGk+1.4MGk=0.28 kN#8226;m
σ=Mmax/w=55.1N/mm2 F2(外立杆荷载)=Nb=10.5KN
F3(工字钢自重)=0.37 KN
Mmax=F1×0.7+F2×1.7=28.4 KN.m
2.2.2.3选型:截面抵抗矩WX= Mmax/f=132.1cm3
选用热轧普通工字钢16号型钢WX= 140.9cm3
截面惯性矩IX=1127 cm4
半截面面积矩SX=80.8 cm3
腹板厚度t=6.0mm
弹性模量E=2.1×104 KN/cm3
2.2.2.4剪应力计算:
τmax=VSx/Ixt=(F1+F2+F3) /Ixt=30.425.8KN(满足要求)
查施工手册,Φ18螺栓的极限承载