_地下室基础开挖施方案

基础开挖施工方案 一、工程概况······································ 二、现场地形条件·································· 三、施工方案······································ 1、现场的具体布署······························ 2、基础开挖工艺流程···························· 3、具体工艺流程的环节叙述······················ 四、基础开挖质量保证措施·························· 五、基础开挖安全保证措施·························· 六、季节性(雨季)施工技术措施···················· 七、现场文明施工·································· 一、工程概况 本工程为西安曲江国际会展中心新展馆一期工程,分为A1、A2、A3和A4四个展厅,均属于钢结构,建筑东西长23.75m,南北宽83.75m,建筑总高度22.7m。基础设计为大开挖,挖深-2.00m,地下室挖深为-10.00 m。基础打开挖已经结束,现二次开挖地下室土方。 二、现场地形条件及施工现场的布置 1、现场地形条件 施工现场“三通一平”已具备条件,水