江苏边城发展集团
成本管理手册
(20 15 版)
编制:成本合约管理中心
编号: JSBC-GLSC-CB-2015-03
时间:2015 年3 月
目 录
第一章 目标成本管理办法·································································································- 3 -
第二章 责任成本管理办法·······························································································- 37 -
第三章 招标工作的成本管理办法···················································································- 64 -
第四章 合同管理办法·······································································································- 81 -
第五章 合同付款及扣款管理办法···················································································- 96 -
第六章 设计变更、工程指令与现场签证管理办法·····················································- 108 -
第七章 工程预算管理办法·····························································································- 122 -
第八章 工程结算管理办法·····························································································- 129 -
第九章造价咨询工作管理办法······················································································- 139 -
第一章 目标成本管理办法
1. 目的
1.1 明确目标成本的制订、监控及调整管理程序,明确各部门的成本控制责任,保
证公司经营目标的实现。
1.2 提高成本管理水平,建立先进合理的目标成本管理体系。
2. 范围
2.1. 本管理办法适用于集团所有项目目标成本管理。
3. 原则
3.1. 市场导向原则:目标成本管理以市场为导向,确保目标利润的实现;
3.2. 准确严谨原则:目标成本指标应科学准确,每项来源都要有充分依据,保证目
标成本的准确可行性;
3.3. 动态管理原则:建设项目的动态成本要及时与目标成本进行比较并纠偏,确保
项目总成本在目标成本控制范围内;
3.4. 逐级递减原则:不同版本的目标成本应以达到规定的基准盈利率为前提,原则
上后一阶段的税前成本总额不得突破前一阶段的总额。
4. 术语和定义
4.1. 目标成本是公司基于市场状况、项目定位规划,结合公司经营计划,根据预期
售价和目标利润进行预先确定的,经过努力所要实现的成本指标。用以控制和指导项
目公司进行动态成本控制,一经确定,非特殊原因不能随意进行更改,确需调整的,
应按流程要求报公司领导审批。
5. 目标成本组成体系
5.1 目标成本的组成体系按照项目开发的一般流程,目标成本划分为以下不同的阶
段:
土地投资论证阶段
项目启动阶段
项目方案设计阶段
项目扩初设计/ 施工图设计阶段
5.2 成本部须在以上不同的阶段编制当期的成本估算,如下:
- 3 -
目标成本(土地版)
目标成本(启动版)
目标成本(方案版)
目标成本(实施版)
以上每个阶段目标成本编制成果均需二级公司