某拆迁安置区建筑楼项目附着式升降脚手架工程
施工安全专项方案
xxx集团有限公司
***年五月
xxxxx区安置区
程序
签 名
职 称
日 期
编制
专业负责人
审
核
项目
技术负责人
公司
技术部门
公司
质量部门
公司
安全部门
批准
公司总工
xxx有限公司
***年五月
目 录
目录························································1
工程概况···········································2
工程概况···········································2
施工布置···········································2
施工要求···········································2
技术保证条件·······································4
编制依据···········································11
施工计划···········································12
施工进度计划·······································12
材料及设备计划·····································13
施工工艺技术·······································15
技术参数···········································15
安装施工方法·······································17
底部、离墙、立面封闭及特殊部位的处理方法···········27
架体提升施工方法···································29
架体下降施工方法···································31
拆除施工方法·······································32
检查验收···········································33
施工安全保证措施···································39
组织保障···········································39
技术措施···········································39
应急预案···········································46
劳动力及设备计划···································53
防雷用电措施·······································54
设计计算···········································55
附件···············································66
第一章 工程概况
一、工程概况
xx拆迁安置区)1#、2#、3#、4#楼项目位于xxx。建筑总高为86.40m,其中标准层为28层,标准层层高为2.85m,附着式升降脚手架从标高+9.15m开始组装,架顶提升至标高+89.50m,待主体施工完成后进行装饰工程附着式升降脚手架又从上往下滑,起到结构施工外防护和外装饰使用等作用。
二、施工布置
1、该系统为一次性安装,安装搭设完成后自行升、降,不占用塔吊工作时间。附着升降脚手架的架体及机位沿建筑结构外围布置。由于建筑结构外围结构变化,相应附着支撑的长度也随着结构发生变化。考虑到该工程的结构特点、外墙形状和建筑物层高,以及提升架的安装原理,每单元整体布置为A、B两片升降,A片设置18个机位,编号为A1至A18,B片设置16个机位,编号为B1至B16,机位平面布置见附后机位平面布置图。本工程的升、降脚手架从标准层第一层顶开始搭设,逐层提升,架顶升至女儿墙顶高处。外墙装饰施工时再从上,下降至搭设位置后拆除。
该工程临边防护、电梯口防护、塔吊防护、水平防护以及内采光井的防护等由项目部自行负责,本方案不做详细说明。
三、施工要求
1、编制施工方案前