PAGE PAGE 5 外挑挂脚手架受力计算 外挑脚手架横向间距1.05m,纵向间距1.5(A316号槽钢间距1.5m)高度,步距1.8m;钢管38.4N/m,扣件15N/只,安全网5N/m2,竹脚手片350N/m2,[16槽钢142.2N/m,风荷载WK=0.524KN/m2,施工均布活荷载2KN/m2, WK =0.7μZμSWO =0.7×1.56×1.2×0.4KN/m2 =0.524KN/m2 1.荷载计算 ①静载(一步) 扣件重: Q1=15N/只×10只=150N 钢管重: Q2=38.4×(1.8×2+1.5+1.5×6)=541.44N 安全网重:Q3=5×1.5×1.8=13.5N 脚手片重:Q4=350×1.05×1.5=551.3N 槽钢重: Q5=1.45×142.2=206.19N 剪力墙重:Q6=1.8×1.41×2×38.4=194.9N 静荷载 Q总=(Q1 +Q2 +Q3 +Q4 +Q5 +Q6)×1.2×0.525/(1.05×1.5) =(0.15+0.5414+0.0135+0.5513+0.2062)×1.2×0.525/(1.05×1.5) =0.552KN/m 活荷载 2×0.525×1.4=1.47KN/m q=0.552+1.47 =2.022KN/m A B C