井研至沙湾联网畅通工程
乐(山)至沙(湾)大道工程
K0+000—K11+540软土地基施工方案
目 录
工程概况及编制依据·················································3
编制依据······················································3
工程概况······················································3
编制原则···························································5
整体施工安排及施工方法·············································6
1.投入机械和人力···················································6
2.总体工期计划·····················································6
3.施工准备·························································6
4.主要施工方案·····················································8
四、质量保证措施·························································11
(1)质量保证体系···················································11
(2)技术保证措施···················································14
(3)主要分部分项工程质量保证措施···································15
五、安全保证措施·························································15
(1)组织机构·······················································15
(2)管理制度·······················································16
(3)工作制度·······················································16
(4)安全技术措施···················································16
六、土方工程雨季施工措施·················································19
七、文明施工措施·························································20
八、环境保护措施·························································20
软基处理施工方案
一、工程概况及编制依据
1.编制依据
1.1.1 依据乐山市通达交通勘察设计有限责任公司,井研至沙湾联网畅通工程乐(山)至沙(湾)大道工程(高新区段)施工图设计(K0+000~K11+540路线全长11.54公里)编制。
1.1.2 国家现行公路工程有关技术标准、规范、规程及法律、法规文件等。
2.工程概况
1.2.1工程简述
乐(山)沙(湾)大道工程(高新区段)是井研至沙湾联网畅通工程的一段。井研至沙湾联网畅通工程位于四川盆地西南边缘乐山市境内,途经乐山市三大经济区井研县、市中区以及高新区至沙湾区,作为乐山市城际交通规划的重要组成部分,对完善乐山公路网、构建西部综合交通次级枢纽、打造乐市半小时经济圈。实现中心城区至周边县(市、区)的快速通达、有效分离城镇区间与过境交通;构建乐山市双百大城市骨架交通干线网络具有十分重要的意义。井研至沙湾联网畅通工程起于国道213线井研五里桥(与仁沐高速连接线相接),经宝五乡、青平镇、下穿绕城高速、全福镇、维洪寺立交、岷江二桥、嘉州大道、绿心路、高新区大渡河大桥、高新区、安谷镇、沙湾大渡河四桥、太平镇、沙湾大渡河三号桥、止于沙湾大渡河一号桥桥头,接省道103线。
乐(山)沙(湾)大道工程(高新区段)K0+000—K11+540起于高新
区郑明村、途经刘河村、二朗
您可能关注的文档
最近下载
- 幼儿园教育质量评价考试题库.docx VIP
- 生物医学检测与仪器.pdf VIP
- CECS156-2004 合成型泡沫喷雾灭火系统应用技术规程.docx VIP
- CECS426-2016 减压型倒流防止器应用技术规程.docx VIP
- CECS40-1992 混凝土及预制混凝土构件质量控制规程.docx VIP
- CECS146-2003 碳纤维片材加固混凝土结构技术规程.docx VIP
- CECS115-2000 干式电力变压器选用、验收、运行及维护规程.docx VIP
- CECS131-2002 埋地钢骨架聚乙烯复合管燃气管道工程技术规程.docx VIP
- CECS194-2006 聚苯模板混凝土结构技术规程.docx VIP
- CECS301-2011 乡村建筑内隔墙板应用技术规程.docx VIP
原创力文档


文档评论(0)