Procast内部教程(Getting Started系列)低压铸造.ppt

Copyright ? ESI Group, 2009. All rights reserved. Copyright ? ESI Group, 2009. All rights reserved. Copyright ? ESI Group, 2009. All rights reserved. Getting started with ProCAST (Low Pressure Die Casting set up) Getting started with ProCAST Outlines The goal of this tutorial is to show a typical ProCAST set up for Low Pressure Die Casting process, including thermal cycling. Process : Duration of the cycle : 280 s Mold opening time : 240 s Part ejection time : 250 s Start time of the die spraying : 255 s End time of the die spraying : 260 s Mold closing time : 270 s Casting temp